Wall-mount

  • Upper and lower bracket locations aligned and mounted first
  • Upper bracket screw holes on the bottom

  • Cabinets are installed before system control box is installed
  • After upper and lower brackets installed, Cabinet "C" installed in the center position first.
  • Next, Cabinets "B", "D", "E", "A" installed in this respective order

Floor-stand

  • Bottom cross beam attached to left-right supports, then top cross beam
  • Relocate original mounting bracket from the top to the middle. Mounting bracket screw holes on top

  • System control box installed before cabinets are installed
  • After upper and lower brackets installed, Cabinet "B" installed just left of the center-position first.
  • Next, Cabinets "B", "D", "E", "A" installed in this respective order